FY27 Municipal Capital Requests - January 2026 - Part 2 of 3 pdf file

Budgets & Finance · Record year 2026 · Record 6f264a84e67483f330

Open original municipal record ↗Open interactive reader

Saved text from 112 source pages. Transcription and OCR may contain errors; verify figures and wording against the original. Retrieved 2026-10-15.

Source page 44

12

Funding

Chapter 3: Interior Repair & Renovation

UO) Design plans funded by Vicky Chaisson
bequest and Select Board

QO) CPA application for repairs to 1902 historical
rooms $150,000

LU) Donations: We want everyone to own part
of the Library

U) Bricks

U) Most of the needed funds were approved at
Town Meeting 2025 and the remaining
balance will be requested at Town Meeting
2026

Source page 45

The
Next
Chapter...

For more information:
Bit.ly/CPLNextChapter

Source page 46

[canton Library Roof and HVAC

frorat PROJECT BUDGET STATUS REPORT
12/12/2025
[                                                                    ‘SUMMARY
PROJECT BUDGET                                                        COMMITTED/ENCUMBERED                                                                                                 INVOICING
REMAINING BALANCE | % BAL to
DESCRIPTION                                                                                                          BALANCE REMAINING                                            (Inc. Retainage) | FUND
Original      Revised     Current     Previous    This Period     Total                Previous  |  This Period     Total       :
[OD.CONSTRUCTION / HARD COSTS:
(01-001-01 Construction Cost                       $   3,114,637.00 |       [$__3.111,500.00 [5 3,111.500.00]    [S$ 3,111,500.00        ~ 1;  2.994 31053] §     - |s 299434053] $    177,335.20   ex
[   ‘01-002-01 Change Orders                  $      - [$s 60175.73|$  60,175.73 | $  130,337.41|$  (70,161.68)| $   60,175.73
TOTAL CONSTRUCTION / HARD COSTS |$_3,114,637.00) |$ 160,375.73 |S 13,171,675.73   3,201,837.41) |$)))) (70,161.68) |S) /3,271,675.73             7994)340.53) 1S         2,994,340S3      177,335.20
[oz SOFT COSTS                                                         I                         I          I                         it          I
[OPM Services
(02-01-01 OPM Services - Design / CA/ Closeout               $    169,065.00 | $     = _[S__169,065.00]$ 169,065.00 $    ~_[S 169,065.00 $       = Js ___17092950[S   4472.50[$ 175,402.00] $     (6,337.00)   435
(02-01-05 OPM - Allowance for Cost Estimator                $    17,000.00 | $     — Ts   17,000.00 | $   4,500.00 | $    - Is   4,500.00 | $     12,500.00 | $   4,500.00 | $     -—_|s   4,500.00 | $     32,500.00   74%]
Subtotal OPM Soft Cost] $    186,065.00 | $     = [$386,065.00] $173,565.00 | $    ~_ [$473,565.00 $     32,500.00 |$ __175,429.50|$____4.472.50|$ 179,902.00] $     6,163.00    3%]
Designer Services
‘02-02-01 Design Services - Architectural Evaluation              $    15,000.00 $     — Ts   15,000.00 [ $   35,000.00] $    - Is   45,000.00 $       ~[s   15,000.00 $     ~ Is   15,000.00 [$       5     0%
(02-02-02 Design Services - Verify Existing Conditions             $    10,000.00 | $     ~Is   10,000.00 | $   30,000.00 | $    -_Is   30,000.00 | $       ~ Is   30,000.00 | $     Is   30,000.00 | $       =     ox}
(02-02-03 Design Services - Architecture                  $    20,000.00 | $     ~ Ts   20,000.00 | $   20,000.00 | $    — Is   20,000.00 | $       Is   20,000.00 | $     = Is   20,000.00 | $       :    0%
(02-02-04 Design Services - Mechanical Engineering              $    13,000.00 | $       $   33,000.00 | $   13,000.00 | $    _ Is   33,000.00 | $       Is   13,000.00 | $     ~ Is   13,000.00 [$       :     0%}
(02-02-05 Design Services - Stone Restoration Detail Documentation        $    20,000.00 | $     — Is   20,000.00 | $   720,000.00 | $    _Is   20,000.00 | $       ~ fs   20,000.00 | $       $   720,000.00 | $       =     0%
(02-02-06 Design Services - Provide Cost Estimate               $     5,000.00 | $     - Is    5,000.00 | $    5,000.00 | $    ~ Ts   5,000.00 | $       -Ts   5,000.00 | $     Is   5,000.00 | $       :     [7
(02-02-07 Design Services - Complete Bldg Documents             $    34,000.00 [$ a2aiai0s[$ 338,141.05[$  138.141.05 |S    ~_[s__ 138,141.05 ['$       = _|s__ 138,141.05 [$s     = _[s338.141.05[$       =    ox
(02-02-08 Design Services - Bid Services                   $     7,500.00 | $     _ Is    7,500.00 | $   7,500.00 | $    — Ts   7,500.00 | $       ~ Is   7,500.00 | $     ~_[s    7,500.00 | $       5     ox
(02-002-09 Design Services - Construction Admin Services            $    15,500.00 | $     _ Is   15,500.00 | $   35,500.00 | $    — Ts   75,500.00 | $       = fs   15,500.00 $     =_|s   15,500.00 $       é     ox]
(02-02-10 Design Services - Reimbursable Expenses              $    10,000.00 | $     Is   10,000.00 | $   30,000.00 | $    —TIs   30,000.00 | $       — Ts   9,001.81 | $    506.19 | $   3,508.00 | $      492.00    3%
(02-02-11 Design Services - Emgergency Repairs with Contractor - 9001,      $       ~_|s_3753559[$   37,535.59 | $   37,535.59 | $    —TIs   37,535.53 [$       Is   37,535.59 | $     ~ Is   37,535.59 | $       =    o%|
(02-002-12 Design Services - Exterior Limestone Failure - 9002           $       = [$12,000.00 ['$   32,000.00 | $   32,000.00 | $    Is   32,000.00 | $       —Ts   32,000.00 | $       $   32,000.00 | $       :     ox|
(02-02-13 Design Services - 9003 Structural                 $      = [$s _1.735.25[$   1,735.25 | $   1,735.25 | $    ~_Is   1,735.25 | $       =~ Ts   1,735.25 | $     Is   1,735.25 [$       =    ox|
(02-002-14 Design Services - Equipment Rebalancing               $       ~_|s 18,200.00 ['$   38,200.00 | $      -_|[s_ 18,200.00 [s   78,200.00 | $        — fs      = [$s     -_[s      ~ Is     18,200.00 [100%
02-02-15 Design Services - Contingency                  $       ~ [$44,545.74 | $   44,545.74 |S   71,435.48 [$__(26,889.74)] $   44,545.74 |S       - [s   28,820.25 | $   3,825.00 | $   32,645.25 | $     11,900.49   27%
Subtotal Designer Soft Cost] $    330,000.00 [$ _238,157.63[$ _368,157.63|$ _376847.37|$ (8,689.74) $368,157.63 | $        =_[s 333,233.95 [$    331.19|$ 337,565.16 | $     30,592.49    8%
lother     ‘Owner Soft Costs
(02-003-01 Environmental Consulting Services                 Ss     3,500.00 $   (200.00)] $    3,300.00]$    3500.00[$ _(200.000] $    3,300.00 S       — Ts    3,300.00 [$     = Ts    3,300.00 $       :     ox
(02-03-02 Biddocs / Advertisting                     gq     1,500.00 | $   (ag2.18)| $    1,017.82] $   i20000/$ _(182.18)]$    3,017.82 | $       — Is    1,017.82] $     ~ Ts    3,017.82 |S       5     Ox
(02-03-03 Owners Insurance - Builders Risk                   $     5,000.00 $ _(5,000.00)] $      __I[s      ~ Is     ~_[s      Is        =~ Is      Is     =_Is      ~ |s     Ox
(02-03-04 Material Testing,                         s     3,500.00|$ __(2,000.00)] $        $      ~{s     — Ts      = Is        — Is      =~ {s     = Ts      =~ {s        =     ox]
02-03-05 Window Testing                            $     2,000.00 | $   (2,000.00) $       - Is       -_13     > 1$       -_|s$         - |s       -_|$      -_|s$       -_|s         =     O%}
Subtotal Other     ‘Owner Soft Costs| $    15,500.00] $ _(9,682.18)| $    4317.82 | $    a700.00[$ _(382.18)| $    4317.82 $        ~ Is    4317.82 | $     = Is    4317.82 | $        =     0%
SOFT COSTS TOTAL |S    331,565,00) |$) 228/475,45) [$111 1)558,540.45) |S) 555,112.37) |S) (9,072.92) [$1 546,040.45) |     12)500,00) [$i 512,981.27) |S) 8,803.69, /S| 521,784.96 |S
[03 Owner incurred Costs
‘03-01-01 Owner Costs                        Is      ~ [s_ 95,146.82 $   95,146.82 | $     = _[s_ 95,146.82] $   95,146.82 | $       ~_[s   95,146.82 | $     - Is   ‘95,146.82 | $       =    0%}
‘Subtotal Owner Incurred Costs| $      = [$95,146.82] $   95,146.82 | $     = [$95,146.82 [$   95,146.82 | $       ~_|s   ‘95,146.82 | $     = _|s   95,146.82 | $       =    ‘0%
[oa CONTINGENCIES
(04-001-01 Owner's Construction Contingencies - 15% Construction Cost        $    467,195.55] $ _(467,19555)|      5                             $        E                              a        -
(04-001-02 Design Contingency- 3% Construction Cost                $     93,439.11] (93,439.11)| $       <                             Ss        2                              $        E
‘Subtotal C       5     560,634.66] $ (560,634.66)| $       5                                $         a                                $         7
[SUMIMARY.
(01 Construction Cost/Hard Cost                  S___3.114,637.00[$ 60,175.73 |$__3,174,812.73|$  3,241837.41[$ (70,161.68) $__3,271,675.73 | $     3,37.00[$  2,994,340.53 | $     =_[s___2,994,34053[$    180,472.20| 5.68%
02 Soft Costs                          $    331,565.00] $  228,475.45|$ _$60,040.45|$ _$55,112.37|$ _ (9,071.92)|$ 546,040.45 | $     34,000.00|$ _512,981.27[$ _8,803.69|$ 521,784.96 |S     38,255.49 6.83%
(03 Owner Incurred Costs                    $       = [$95,106.82 1S   95,146.82 | $      - [$95,106.82 |$        $       - Is   95,146.82 | $     - Is   95,106.82 | $       -   0.00%
(04 Contingencies                                $            '$_ (560,634.66)| $           $          $         $           $

ed Esti

‘Appropriation by Town of Canton
Current Project Budget (TPC) $
Funds Transferred to Interior Project_$

Source page 47

TOWN OF CANTON
FORM B — FISCAL 2027
CAPITAL PROJECT / EQUIPMENT REQUEST

DEPARTMENT:

Fire

EH

SUBMITTED BY: |

Wendell Robery.

PROJECT / EQUIPMENT TITLE:
Replcement of 2001 E-One Ladder

TOTAL PROJECT / EQUIPMENT COST:
(Must be at least $5,000):

Any contingency should be explained below

§ 1,810,000.00

DESCRIPITION:

New Tower Ladder
Funding- borrowing and ambulance receipts-TBD

What is the request for? Example: 4 police cruisers. What are the funding sources (if more than one)?

PURPOSE AND JUSTIFICATION:

the fleet where the role is applicable.

See attached sheet

Why the department needs this item. If additional space is needed for justification, please add a second page.
Does this further the Town’s Green Policy? Examples: We reviewed the ‘greener’ options; however, the internal combustion engines
remain a requirement for patrol vehicles that must run for longer periods without the ability to charge. We do have hybrid vehicles in

NEED CLASSIFICATION: (Check all that apply)
 Required for Safety
C Required by Law or Mandate
 Improve/Expand Service or Increased Efficiency
Planning Classification:

Planned project or replacement (on the prior vear'{>|
* if not planned, please explain in justification

Department Priority Rank:
(Please rank this request out of your total requests for
this year: #1 as top priority)

Priority #_/ of # et

Expected Useful Life:

20 + Years

Impact on Dept. Operating Budget:
No Impact    [=]      by$

Impact to Dept. Revenue:

No tmpact   by S

For motorized equipment: Was an electric or hybrid option considered? Please explain below

OTHER COMMENTS OR INFORMATION: (Attach supporting documentation including quote}

This fire truck is not available in an electric or hybrid version.

Source page 48

of Canton, Massachusetts

99 Revere Street, Canton, MA 02021
ANDY MORGAN                                      Business: (781)575-6654                                       EDWIN J. FREITAS
Deputy Chief Administration                                                                                                                              Deputy Chief Operations
amorgan@town.canton.ma.us                                E.WENDELL ROBERY                                  efreitas] @town.canton.ma.us

Chief of Department
wrobery@town.canton.ma.us

The Canton Fire Department currently operates two ladder trucks:

e Ladder 1: Stationed at Station 1, District 1
e Ladder 2: Stationed at Station 2, District 2

Ladder 1 is a 2001 E-One 100’ straight-tip aerial that has served the department reliably for 24
years. It currently has 33,000 miles, with 5282 engine hours which equates to 211,800 miles. By
the time a replacement is delivered—expected in late 2029 due to a 44-month lead time from
contract signing—Ladder 1 will be 28 years old, exceeding our department’s typical replacement
target of 25 years for aerial apparatus.

Replacement Recommendation:

We recommend replacing Ladder 1 with a tower ladder (platform aerial), which provides
enhanced functionality, safety, and operational capabilities compared to a straight-tip ladder.

Justification for Tower Ladder:
1. Enhanced Firefighter Safety

e Enclosed Platform: The tower ladder offers a secure, stable platform for firefighters to
operate from, minimizing the risk of falls, especially in adverse weather conditions.

e Reduced Physical Strain: Firefighters and equipment can be elevated into position in
the bucket, rather than climbing the aerial with tools, reducing fatigue and risk of injury.

2. Improved Operational Capabilities

e Precision Water Delivery: The platform allows for accurate targeting of water streams,
increasing efficiency in fire suppression efforts.

e Versatility in Rescue Situations: The bucket can be positioned precisely to facilitate the
removal of victims from roofs, upper floors, or elevated platforms—particularly
important when stair access is unavailable or compromised.

PLEDGED TO FIRE PREVENTION

Source page 49

3. Rescue & EMS Advantages

* Patient Immobilization & Extraction: The tower ladder serves as a critical rescue
platform for patients who require immobilization and cannot be moved via conventional
means, such as stairs or ground ladders.

4. Long-Term Value
e While the initial cost of a tower ladder is typically higher than a straight-stick aerial, the

increased capabilities, safety features, and potential for dual-purpose use (fire suppression
and technical rescue) provide long-term operational value and flexibility.

Conclusion:

Ladder 1 has served the department and the community well for over two decades but will have
surpassed its ideal service life by the time a replacement is delivered. Transitioning to a tower
ladder for its replacement aligns with our commitment to firefighter safety, operational
efficiency, and readiness for complex rescue scenarios,

Source page 50

Robery, Wendell

Et      a                                   REDE           a             Se
‘From:                              Bruce King <bking@greenwoodev.com>
‘Sent:                                    Wednesday, September 24, 2025 11:39 AM
To:                                            Robery, Wendell
Subject:                              TOWER PRICE

CAUTION: This email originated from outside your organization. Exercise caution when opening attachments or on
clicking links from unknown senders.
Good morning, Chief.

The price for your E-One 92’ tower is $1,799,995.00. One million seven hundred ninety-nine thousand nine hundred
ninety-five dollars. The estimated time for completion for such tower is (44) month once a contract is signed by both
the Town/Fire department of Canton, Ma, and Greenwood Emergency Vehicles.

If you have questions or need further information. Please contact me.
Thank you.
Be well and let’s be careful out there.
Bruce King

Regional Sales Manager
Cell: 781-956-1916/ bking@greenwoodev.com

GREEnwoOD

EMERGENCY VEHICLES

530 JOHN L. DIETSCH BOULEVARD
NORTH ATTLEBRRO, MA 02763

GP aivocton Smee PRS

Disclaimer

The information contained in this communication from the sender is confidential. It is intended solely for use by the recipient and
others authorized to receive it. If you are not the recipient, you are hereby notified that any disclosure, copying, distribution or
taking action in relation of the contents of this information is strictly prohibited and may be unlawful.

Source page 51

TOWN OF CANTON
FORM B — FISCAL 2027
CAPITAL PROJECT / EQUIPMENT REQUEST

DEPARTMENT:                                                   SUBMITTED BY:
Fire                                                     [+]
Wendell Robery
PROJECT / EQUIPIMENT TITLE:                                     TOTAL PROJECT / EQUIPMENT COST:
Feasability Study                                                   Must be at least $5,000):

Any contingency should be explained below

$ 110,000.00

DESCRIPITION:
What is the request for? Example: 4 police cruisers. What are the funding sources (if more than one)?

Feasability Study
Funding-cash capital

PURPOSE AND JUSTIFICATION:

Why the department needs this item. [f additional space is needed for justification, please add a second page.

Does this further the Town’s Green Policy? Examples: We reviewed the ‘greener’ options; however, the internal combustion engines
remain a requirement for patrol vehicles that must run for longer periods without the ability to charge. We do have hybrid vehicles in
the fleet where the role is applicable.

See attached sheet.

NEED CLASSIFICATION: (Check all that apply)              Department Priority Rank:
,                                                                (Please rank this request out of your total requests for
C] Required for Safety                                               this year: #1 as top priority)

C] Required by Law or Mandate                             Priority #  2 of# 2

 Improve/Expand Service or Increased Efficiency
ra)                                                               Expected Useful Life:

Planning Classification:                                            20 + Years                        [x]
Planned project or replacement (on the prior year'{>]
* If not planned, please explain in justification

Impact on Dept. Operating Budget:                          Impact to Dept. Revenue:
No Impact     na      by$                          .                   No Impact      [x]    by$

For motorized equipment: Was an electric or hybrid option considered? Please explain below

OTHER COMMENTS OR INFORMATION: (Attach supporting documentation including quote)

SUBMIT

Source page 52

of Canton, Massachusetts

99 Revere Street, Canton, MA 02021
ANDY MORGAN                                     Business: (781)575-6654                                     EDWIN J. FREITAS
Deputy Chief Administration                                                                                                                                         Deputy Chief Operations
amorgan@town.canton.ma.us                                E.WENDELL ROBERY                                  efreitas 1] @town.canton.ma.us

Chief of Department
wrobery@town.canton.ma.us

Request for Feasibility Study Funding — Canton Fire Department

The Canton Fire Department is requesting $110,000.00 to conduct a feasibility study to evaluate
the current and future space needs of our facilities and determine the most cost-effective solution
to address them.

We currently operate out of two fire stations:

e Station 1 (Headquarters): 99 Revere Street — built in 1978 and renovated in 2004
e Station 2: 7 Sassamon Street

Due to significant growth in operations and staffing, Station 1 has exceeded its functional
capacity. To meet our current operational needs, we are incurring ongoing expenses to rent:

e An office trailer for the EMS Coordinator                                                    :
e 4,400 square feet of warehouse space for vehicle repair, emergency management trailer,
lighting plant, and ciitical storage

This space shortfall is not sustainable long-term and negatively impacts our operational
efficiency and readiness. In response, we propose a professional feasibility study to determine
whether:

It is economically viable to renovate or expand the current stations

A complete rebuild on the existing footprint would be more cost-effective
There is potential to acquire adjacent land to facilitate expansion-

e Cost estimates and comparative analysis for each option

The attached Request for Information (RFI) outlines the scope of work expected from the
feasibility study. The findings will provide the necessary data and recommendations to support
future planning, budgeting, and possible capital funding requests.

The requesting amount of $110,000.00 is based on the following feed back from the RFI and
some prices of towns requesting a similar study:

Town of Weston $92,000 — 2022

PLEDGED TO FIRE PREVENTION

Source page 53

Town of Rockland $165,000 -3 stations and land acquisition.
RGB Architects $137,000

Five Bugles Design $ 49,500

We appreciate your consideration of this request and look forward to your support in helping us
better serve the community through improved facilities.

Source page 54

Town of Canton

REQUEST FOR INFORMATION

Fire Station Feasibility Study

September 8, 2025

RESPONSE DUE: October 2, 2025 5:00 PM

Source page 55

Town of Canton
RFI - Fire Station Feasibility Study                                                                               Page |1

Request for Information (RFI): Fire Station Feasibility Study

PART |. GENERAL INFORMATION

1.3

PROCUREMENT DESCRIPTION

The Town of Canton (Town), is requesting Information from qualified parties to inform its
stakeholders on the overall cost of services to perform a feasibility study on its two existing Fire
Stations.

Respondents to this Request for Information (RFI) are invited to respond to any or all of the questions
in this document. Responses to this RFI shall serve solely to assist the Town of Canton in
understanding the current state of the marketplace with regards to the solicited information or to
inform the development of a possible solicitation for a Request for Proposals (RFP) or Request for
Quotes (RFQ) in the future. This RFI does not in any way obligate the Town of Canton to issue or
amend a solicitation or to include any of the RFI provisions or responses in any solicitation.
Responding to this RFI is entirely voluntary, and will in no way affect the Town of Cantons
consideration of any proposal submitted in response to any subsequent solicitation, nor will it serve as
an advantage or disadvantage to the respondent in the course of any RFP or RFQ that may be
subsequently issued or amended

PURPOSE

The purpose of this RFI is to elicit the advice and best analysis of knowledgeable persons in the vendor
community to enable the Town of Canton to craft a potential future solicitation for feasibility studies
of its two fire stations. This RFI solicitation seeks responses from vendors who can offer information
about feasibility studies which meets the criteria and objectives detailed below.

OBTAINING THE REQUEST FOR QUOTATIONS
The Request for Information shall be available beginning on September 8, 2025.

The RFI and related documents may be obtained from the Planning Department by emailing Connor R
Murphy at cmurphy@town.canton.ma.us.

PART 2. INSTRUCTIONS TO PROPOSERS

2.1

RESPONSE SUBMISSION REQUIREMENTS
Email PDF version of the response, by 5:00 PM on October 2, 2025, including price, clearly marked:
“Response for Canton Fire Station Feasibility Study” within the subject line of the email to Connor R.

Murphy, Town Planner at cmurphy@town.canton.ma.us

The Response must contain the following information:

Source page 56

Town of Canton
RFI - Fire Station Feasibility Study                                                                           Page |2

2.3

2.4

A. Cover Letter: a cover letter introducing the Consultant (firm) and the proposal Consultant
team, including sub-consultants, and identifying the project manager and the name, title,
address and telephone number of the person with authority to negotiate and contractually
commit to all services.

B. Scope of Services: A proposed scope of services that is detailed and responsive to the

project as outlined in this request for quotes.
* The scope should be detailed by tasks (and subtasks if appropriate).
+ Include an estimated schedule of hours which the Consultant expects to spend on the
various project tasks and sub-tasks.
* Town staffing resources will support this work. The proposed scope should, to the extent
necessary, define what organizational support is needed from the Town.

C. Project Team: Provide the names and specific educational backgrounds, qualifications and
expertise of all professional members of the Consultant's and sub-consultant’s (if any)
project team who will perform the work related to some or all the project tasks. Identify the
person who will be the project manager with ultimate responsibility for the work.

D. Relevant Experience and Prior Performance: Provide details of relevant experience and
prior performance for all the members of the Consultant team, including the subconsultant’s team
members if any.

E. References: Respondents shall provide at least three references.

F. Certificates: Include signed certificates of non-collusion and tax compliance attached to
this RFP.

G. Proposed Fee: Provide the proposed fee for the entirety of all services proposed, including
but not limited to travel, meetings, telephone, postage, and reproduction.

H. Rates: The hourly rates to be charged by the Consultant for services performed by each team
member.

SIGNATURES

A Response must be signed as follows: |) if the responder is an individual, by her/him personally; 2) if
the responder is a partnership, by the name of the partnership, followed by the signature of each
general partner; and 3) if the responder is a corporation, by the authorized officer.

QUESTIONS, CHANGES, MODIFICATIONS AND WITHDRAWALS

Source page 57

Town of Canton
RFI - Fire Station Feasibility Study                                                                               Page |3

2.4.1 QUESTIONS/REQUESTS FOR CLARIFICATION
Questions concerning this Request for Information must be submitted to Connor R Murphy at
cmurphy@town.canton.ma.us by 10:00 AM on September 15, 2025. Written responses will be e-

mailed to all proposers on record as having received the Request for Information by September 18,
2025.

2.4.2 CHANGES
If any changes are made to this Request for Information, addenda will be issued. Addenda will be e-
mailed to all proposers on record as having obtained the Request for Information.

2.4.3 MODIFICATIONS AND WITHDRAWALS
A proposer may correct, modify, or withdraw a response by written request submitted to the Town of
Canton prior to the time and date set for bid opening.

Modifications must be submitted via E-Mail clearly labeled "Modification No.__" to the address listed in
part one of this section. Each modification must be numbered in sequence, and must reference the

Request for Proposal.

PART 3. SCOPE OF WORK

3.1 OVERVIEW AND PURPOSE
The Town of Canton is seeking to gather this Request for Information in support of Capital Planning
initiatives in funding a Feasibility Study. The information received will be to inform the Town of the
specific costs per the scope of work as noted below, supporting the capital request, which will lead to
the required funding supporting a potential RFP or RFQ to be issued.

3.2 BACKGROUND INFORMATION
Canton is a community located approximately 5 miles southwest of Boston, with a population of
24,370, according to Census 2020 figures’. Its population increased 10.3% over the previous 10 years,
which is a stronger rate of growth than projected in the Master Plan (2020)”. The town is an
established and maturing suburb, characterized by lower densities throughout the community with a
limited amount of vacant land that is developable*. Canton has a majority of single-family home
developments (60%) on moderately-sized lots, with a relatively affluent population’, It is home to major
employer and retail centers with connectivity to two commuter rail stations in the town center, access
to highways I-95 and I-93, and Route 716 Massachusetts Bay Transportation Authority (MBTA) bus
service’. The Town is governed by a five-member Select Board and Open Town Meeting. Daily
management is by the Town Administrator appointed by the Select Board.

1 https://www.census.gov/quickfacts/fact/table/cantontownnorfolkcountymassachusetts/PST040219

2 https://www.town.canton.ma.us/DocumentCenter/View/3884/Canton---People-Snapshot-PDF

3 http://www.mapc.org/wp-content/uploads/2017/09/Massachusetts-Community-Types-Summary-July_2008.pdf
4 https://www.town.canton.ma.us/DocumentCenter/View/3883/Canton---Housing-Snapshot-PDF
5 https://www.town.canton.ma.us/DocumentCenter/View/3878/Canton---Transportation-Snapshot-PDF

Source page 58

Town of Canton
RFI - Fire Station Feasibility Study                                                                             Page |4

3.3 SCOPE OF SERVICES
Background

Canton Central Fire Station - 99 Revere Street

Canton Central Fire Station (HQ) was built in 1974 and had a major renovation around
2006. Routine building maintenance and repairs projects have occurred since then. The
station sits on 1.65 acres. There is one structure that is 2-3 stories in height and

multiple curb cuts,

Canton Fire Station 2 — 7 Sassamon Street

Fire Station 2 was built in 1964. The site is approximately |.3 acres which abuts
residential properties.

Due to the constraints of the Headquarters site, the Town wishes to study the future
needs of the Fire Station Headquarters and Station 2 in order to identify possible shared
solutions to problems such as vehicle storage, parking and access, and to define the
future building footprint, should expansion/reconfiguring of the Fire Station
Headquarters/ Fire Station 2 be necessary. Alternative sites are not part of this study.

Phase |: Conditions Assessment and Development of Design Program
Upon notification to proceed, the Designer shall:

|, Review existing conditions, applicable documentation, physical investigation of the
existing Canton Fire Station buildings (HQ and Station 2), parking lots, and land.

2. Assume given the age of the buildings new MEP systems are required in the long-
term planning and the cost estimate needs to reflect this. A Net Zero building shall
be considered as one of the options.

3. Assess ceiling/acoustical tile, floor, wall and roof systems.

4. Determine compliance with applicable codes, accessibility, and adequacy of facilities
for both genders.

5. Schedule meetings with a working group including appropriate Canton Fire
Department staff members, at least | Building Committee member and other Town
employees, as required, to learn about the activities of the Fire Department, how
the Fire Stations are currently used, current space and parking deficiencies and
future programmatic and space needs.

Source page 59

Town of Canton
RFI - Fire Station Feasibility Study                                                                             Page |5

6. Through the Canton Facilities Department, review with the Fire Chief /Town
Administrator, the fire department current staffing, and staffing and growth
projections for the Fire Department.

7. Provide a tabular (spreadsheet) detailing the space needs program that itemizes the
net area for all spaces required in the building(s) and any appurtenant structures.
This should include apparatus bay, living areas, business areas, mechanical spaces,
etc. Assemble program to indicate gross area by use within the building and overall
building gross square footage.

a. For all major spaces provide a space needs diagram to illustrate the size
and capability of the programmed areas. Space diagrams should be
provided for at least; Apparatus bays, equipment storage, washdown
areas, meeting or training rooms, kitchen/dining, sleeping quarters,
showers and toilet rooms for sleeping areas, and any other significant
area.

b. Provide a list of all rolling stock and including Ladder and pumper trucks
as well as other equipment requiring garage space such as boats, ATV's.

c. Identify equipment to be purchased outside the construction contract but
to be included in the Total Project Cost such as laundry equipment,
furniture, radio systems, etc.

d. With the space diagrams and with a program narrative, identify special
mechanical and electrical criteria for equipment or system design that
require significant space and/or construction cost; e.g. specialized
ventilation, lighting, plumbing, power supplies, etc.

8. Develop an overall Master Plan for the proposed renovation and/or an expansion of
the existing facilities and/or a new facility that meets public safety needs, staffing and
growth projections as defined by the Town Administrator/Fire Chief. When
evaluating the various construction options, all types of construction, public access,
abutter concerns and aesthetics shall be considered.

9. Identify and prioritize the most urgent needs to be addressed with regard to both
physical plant and programmatic needs, highlighting any existing safety issues and non-
conformities.

10. The cost estimate shall include energy-efficient and cost-efficient configurations for
infrastructure building systems including but not limited to HVAC, plumbing, electrical,

Source page 60

Town of Canton
RFI ~ Fire Station Feasibility Study                                                                             Page [6

fire protection and information/communication, Recommend options with current
energy saving systems. Develop recommendations for energy-efficient and cost-efficient
configurations for infrastructure building systems included but not limited to HVAC,
plumbing, electrical, fire protection and information/communication. Building system
recommendations should take into account Cantons Climate Action and Resilience plan
goals.

II . Assess fire protection design and living quarters, including, but not limited to,
equipment and uniform maintenance and cleaning, equipment storage, air refilling
stations, and building access/egress.

12. Evaluate existing sites, including parking areas, driveways, walkways, common areas,
public access, etc. Identify site opportunities and constraints relevant to possible
expansion of the existing buildings.

13. Develop the most cost-effective phased plan for assessing renovations and/or for
providing additional space:

a. Analyze the practicality of phased infrastructure upgrades and the
integration with existing or new systems.

b. Propose an overall schedule and sequencing for a comprehensive plan at
both locations.

c. Consideration and cost estimate to keeping the station operational
during the construction projects.

14. Incorporate removal of suspect asbestos containing material (ACM) and/or any
other hazardous material in the phasing plan. (No Testing has been performed.)

15. Conduct a review of other recently renovated or new Fire Stations in communities
in Massachusetts that are comparable to Canton in size and program requirements to
determine "best practices" related to their design.

16. Estimate pricing of various options and/or components of a phasing plan.

Phase II: Development of Conceptual Schematic Drawings and Cost
Estimates

|. Provide the Building Renovation Committee with Conceptual Schematic Drawings
based upon agreed-upon programmatic elements. Such drawings must comply with
all legal requirements such as, but not limited to, applicable Building Codes and local
regulations.

Source page 61

Town of Canton
RFI — Fire Station Feasibility Study                                                                                  Page |7

2. Provide estimates of the cost of the work and scope shall include both Estimated
Construction Cost (ECC) and Total Project Cost (TPC) that are proposed in the
Conceptual Schematic Drawings for presentation to the Building Committee and use
at Town Meeting.                                ‘                                     ;

Phase Ill: Development of Presentation Drawings and Related Materials
Provide and present draft Conceptual Drawings, renderings and related materials to the
Building Committee and the Select Board at one of their scheduled night meetings. This
presentation shall be prepared in a format appropriate for Town Meeting.
Deliverables:                                             ,

At completion of each Phase, the Designer shall submit an electronic DRAFT copy to
the Facilities Department. Participate in a follow-up review meeting, which may be a
public meeting, to discuss and review comments for each Phase.

The Designer shall participate in one (1) public meeting of the Building Renovation
Committee (BRC) and one (1) public meeting of the Select Board, both which will be in
the evening hours, to present the Final Draft Report and presentation materials. The
Final Report shall reflect input and comments from both these meetings. Final Phase
Report shall consist of six (6) hardcopies and three thumb drives in a PDF format.

Staff Role

Town of Canton staff, primarily the Town Planner, will be closely involved, but the Consultant is
expected to devote the time needed to conduct research, write documents, and participate in regular
check-in meetings. Staff will provide documentation, personal knowledge, reasonably necessary
baseline data, GIS data and layers, and existing town plans in progress or recently completed.

TIMETABLE

Request for Information issued                                      September 8, 2025
All questions due by                                                September 15, 2025
Question responses provided                                     September 18, 2025

Response Due Date                                           ~ October 2, 2025

Source page 62

TOWN OF CANTON
FORM B — FISCAL 2027
CAPITAL PROJECT / EQUIPMENT REQUEST

DEPARTMENT:                                      SUBMITTED BY:

MIS
Louis Jutras

PROJECT / EQUIPMENT TITLE:                   ;                TOTAL PROJECT / EQUIPMENT COST:
Must be at least $5,000):

Any contingency should be explained below

Library Community Room A/V

§ 70,000.00

DESCRIPITION:
What is the request for? Example: 4 police cruisers. What are the funding sources (if more than one)?

Interactive screens, sound, touch panels for community room

PURPOSE AND JUSTIFICATION:

Why the department needs this item. If additional space is needed for justification, please add a second page.

Does this further the Town’s Green Policy? Examples: We reviewed the ‘greener’ options; however, the internal combustion engines
remain a requirement for patrol vehicles that must run for longer periods without the ability to charge. We do have hybrid vehicles in
the fleet where the role is applicable.

Equipment has been installed since 2003.  Projector is failing, rear speakers don't work, front screen
has experienced issues lowering and raising.

NEED CLASSIFICATION: (Check all that apply)              Department Priority Rank:
;                                                                     (Please rank this request out of your total requests for
[__] Required for Safety                                                this year: #1 as top priority)

[_] Required by Law or Mandate                                 Priority #7 of #  +

im Improve/Expand Service or Increased Efficiency                                 .
Expected Useful Life:
Planning Classification:                                                   10 to 19 Years

Unplanned project or replacement
* If not planned, please explain in justification

Impact on Dept. Operating Budget:                         Impact to Dept. Revenue:
No Impact           by $ 0.00                               No Impact           by $ 0.00

For motorized equipment: Was an electric or hybrid option considered? Please explain below

OTHER COMMENTS OR INFORMATION: (Attach supporting documentation including quote)

Issues started early in 2025. Anticipated that this equipment would be part of the library renovation
project but it is not

SUBMIT

Source page 63

V-T

Technology Simplified For Better

Audio Visual | Collaboration
Event Technologies | Physical Security

Rob Bernstein

Proposal To:

Canton Public Library

For:

Community Room Upgrades

By:

rob@rev-t.com

June 12, 2025
R25P255 Valid Until: June 26, 2025

Source page 64

REV-T

Technology Simplified For Better

** Due to the recent implementation of tariffs on goods originating from China, Mexico and Canada, pricing on this proposal is valid for a
period of 14-days from origination.

We understand the impact that price adjustments can have on your business, and we are committed to maintaining transparency and
providing you with the best possible service during this time. **

Please note the following, which apply to all REV-T proposals:

1. **Exclusion of Software Licenses:**

Only the software licenses specifically mentioned in this proposal are included. No additional software licenses are provided.
2. **Client Responsibility for MS Teams Room and Zoom Room Licensing:**

The client must purchase and deploy any necessary MS Teams Room or Zoom Room licenses before REV-T arrives on-site for
installation.                                                                     :

3. **Client Responsibility for Network Functionality:**

The client is responsible for ensuring network functionality, not provided by REV-T, prior to the installation of any hardware.
4. **Recommendation for Software Licensing Testing:**

We recommend that the client test all software licenses at least 24-hours before REV-T's scheduled hardware installation, as license
recognition by the network may take up to 24-hours.

* All labor on this proposal is at Prevailing Wage labor rates per the supplied wage schedule *
* Pricing of the project follows the MA State Contract OFF50 guidelines*
* Any electrical work (120v) would be done by others. REV-T is strictly a low-voltage integrator *

||Owner Furnished Equipment (OFE) Disclaimer

REnVisioning Technology, LLC (REV-T) is not responsible for the functionality, compatibility, performance, or condition of any Owner
Furnished Equipment (OFE) provided by the client.

The client assumes full responsibility for ensuring that all OFE is in proper working condition, meets the necessary technical
requirements, and is available on-site as needed for integration.

||REV-T will make reasonable efforts to incorporate OFE into the project as specified in the proposal; however, any delays, additional
labor, or modifications required due to OFE-related issues may result in additional charges.
REV-T is not liable for any malfunctions, damages, or failures of OFE that impact the overall system performance.

By accepting this proposal, the client acknowledges and agrees to these terms regarding OFE.

Confidential Proposal
R25P255 Version 1.0e June 12, 2025
2of 10 Valid Until: June 26, 2025

Source page 65

REV-T

Technology Simplified For Better

COMMUNITY ROOM

~ SCOPE

Scope of Work:

Client has requested AV upgrades and additional functionality to a large divisible meeting space.

For purposes of this proposal we will call the main area (which has the drop-down screen and projector) "Side A", and the back section
of the room "Side B".

Client would like the ability to divide (Side A or Side B operating autonomously) or combine (Side A and B) the spaces.

For the purposes of this initial proposal we are assuming the existing projector and screen will remain, and an additional interactive flat
panel will be added to Side A.

If there is a desire to replace either the existing Epson projector and/or Draper screen, we can add that as an option.

e@ The "old" AV system will be decommissioned with the exception of any equipment listed as "Owner Furnished Equipment/OFE"
on this proposal
© Any decommissioned equipment will be left for the town to reuse or dispose of
e An 86" Interactive panel will be installed on the wall in the "A" side of the room (where the projection screen is currently)
© UHD 4K (3840 x 2160) Native Resolution
LCD Panel with Infrared Touch
3x HDMI| 1x VGA|1x DisplayPort
2x USB-C Inputs with DP Alt Mode
400 nits Brightness | Anti-Glare Glass
SMART Ink Software Included
Integrated Dual 20W Speakers
Built-In Wi-Fi & Bluetooth
© Advanced Replacement Warranty, free technical support
e An8g6" LCD display will be installed in the "B" side of the room in the small alcove at the end of the room
© Two (2) 7" touch panels will be installed, one each in Side A and SideB
© These touch panels will give the room users fast and logical control over the new AV system
© Finallocations TBD
e The existing Extron wall plate in Side A will be removed and replaced with a new and more current MXNet one
© This same wall plate will also be installed in Side B (location TBD)
© The wall plate has the following connections on it:
8 HDMI
e USB-C
a 3.5mm Audio
o lIfauser still needs a VGA connection, a VGA to HDMI cable can be used
e Twelve (12) ceiling speakers will be installed in the drop-tile ceiling, replacing the existing speakers
© Six (6) speakers will cover Side A
© Six (6) speakers will cover Side B
© The speakers will have the ability to be combined (A+B) or divided (A and B)
e In addition to the existing two (2) Shure wireless systems in the rack, another Shure QLX-D receiver will be added
© The new receiver will have both handheld and lavalier/body pack microphones
© Note that the handheld and lavalier/body pack mics cannot be used at the same time with the same receiver
© ANRF Venue Architectural antenna will be installed for superior wireless mic signal reception in both Side A and B
© AQSYS Core DSP will be installed in the rack to handle system control and audio processing
e Two (2) Crestron AirMedia Wireless Collaboration systems will be installed, one (1) for Side A and one (1) for Side B
© Each AirMedia will allow for wireless content sharing to the room via USB-C dongle
© Each room will have two (2) dongles

00009 09 OO

Confidential Proposal
R25P255 Version 1.0e June 12, 2025
3of 10 Valid Until: June 26, 2025

Source page 66

Technology Simplified For Better

© Ifthe rooms are being used in "Combine" mode, the AirMedia from Side A will be active

© The function of the AirMedia system is to eliminate the need to physically plug a laptop into a wall plate to share content
e Anew Blu-Ray/DVD/CD/SD player will be installed in the rack

© Ifthe rooms are in "Combine" mode, the player will present in both spaces

© Ifthe rooms are in "Divide" mode, the player will be viewed in Side A

To be completed by others Prior to REV-T's Installation:

- Network drops behind each display location

- Install (1) dual 120V, 20Amp outlet at Room A's display location.
- Install (1) dual 120V, 20Amp outlet at Room B's display location.

AV SYSTEM

IMAGE        QTY DESCRIPTION                                                                                                  PRICE = PRICE EXT
|      1 LGElectronics 86" UHD, 330 nit, Commercial Flat Panel Display with 3-Year Warranty           $2,217.00 $2,217.00
HE      1 Chief Micro-Adjust Tilt Wall Mount, Large                                                                    $280.00       $280.00

Pe |     1 SMART Technologies 86" interactive display with embedded OS (GMS), 400 nit brightness,

2,615.00     2,615.00
Integrated Dual 20W Speakers                                                                         §              $

l         J 1. SMART Technologies Wall Mount for Interactive Display Panel                                            $55.00         $55.00
—_      1    Qsc   Unified Core DSP with 24 local audio 1/0 channels, 128x128 total network /O                $3,358.00 $3,358.00
channels with 8x8 Software-based Dante license included, USB AV bridging, dual LAN ports
osc

Pa         2 QSC Core 110 UCI Deployment Software License, Perpetual                                               $188.00       $376.00

coe
a        2 QSC 7” PoE Touch Screen Controller for In-Wall Mounting (Black)                                    $1,434.00 $2,868.00
eahsia        1 Shure Bodypack and Vocal Combo Wireless Mic System                                                   $1,474.00 $1,474.00
i                     1 RFVenue Diversity Architectural Antenna for Wireless Microphones                                          $587.00        $587.00
“=m. «61 sCrestron X-Series Amplifier, 500 W                                                                     $900.00      $900.00
M1} 12 JBLProfessional 4.5" Compact 2-Way Ceiling Speaker                                                    $125.00 $1,500.00

Confidential Proposal
R25P255 Version 1.0e June 12, 2025
4of 10 Valid Until: June 26, 2025

Source page 67

Technology Simplified For Better

IMAGE       QTY DESCRIPTION                                                                                       PRICE    PRICE EXT

2      AirMedia Wireless Collaboration Bundle with (2) Connect Adapters                                   $2,617.00 $5,234.00

1 Denon Blu-Ray, DVD & CD/SD/USB Player                                                                     $479.00       $479.00

b@|?

AVPro Edge Control Box for MXNET System                                                                 $434.00       $434.00
4  AVProEdge MXNet 1G Evolution II Encoder                                                              $791.00 $3,164.00
|       3. AVProEdge MXNet 1G Evolution II Decoder                                                                  $791.00 $2,373.00

AVPro Edge MXnet Evolution II AV-over-IP wall plate encoder with switchable HDMI and

<i

$830.00 $1,660.00

USB-C inputs

Pp .    Netgear 24x1G PoE+ 480W 2x1G and 4xSFP+ Managed Switch                                          $1,755.00 $1,755.00
REV-T 4   REnVisioning Technology, LLC Miscellaneous Installation Items including cable, wire,       $1,650.00 $1,650.00

Meteora arn             connectors, etc.                                                                                                                                  _—              _
hw      2 OWNER FURNISHED Miscellaneous Shure QLX-D Wireless Microphone Receivers                    $0.00          $0.00
cms = 1) OWNER FURNISHED Miscellaneous Shure UA844 Antenna Distributor                               $0.00         $0.00
Ss     2 OWNER FURNISHED Niscellaneous WilliamsAV Digi-Loop Assisted Listening                       $0.00         $0.00
1 OWNER FURNISHED Miscellaneous Equipment Rack                                           $0.00        $0.00

EQUIPMENT TOTAL                                           $32,979.00
LABOR TOTAL                                                                                         $34,648.32
COMMUNITY ROOM TOTAL                                                               $67,627.32

Confidential Proposal
R25P255 Version 1.0e June 12, 2025
5 of 10 Valid Until: June 26, 2025

Source page 68

REV-T

Technology Simplified For Better

OPTION #1: VIDEO CONFERENCING

SCOPE
This option would add in-room video conferencing capability from either side of the room (A or B).

e APTZcamera would be installed in both Side A and Side B
© Ifthe rooms are divided either or both rooms would have video conferencing capability
Two (2) small room PC's would be installed in the equipment rack behind the stage area
© Each PC would operate a single room (A and B)
A 4-foot linear mic array would be installed in both Side A and Side B for voice pick up
If Side A and B are combined, the PC for Side A would be used for video conferencing
A 10.1" touch panel would be installed in each of the spaces (A and B) to control the video conferencing system
© Final location TBD
© The rooms will be Zoom or Teams Rooms to allow for room users to easily launch/join a call
© The codec is TBD

AV SYSTEM

IMAGE       QTY DESCRIPTION                                                                                    PRICE — PRICE EXT

2 Logitech 10.1" PoE Meeting Room Touch Controller                                                    $726.00 $1,452.00

isa

AVer 12X 4Kp60 Auto Tracking PTZ Camera w/ NDI                                                                 $3,064.00 $6,128.00

6 AVProEdge MXNet 1G Evolution Il Encoder                                                             $791.00 $4,746.00

me      4  AVProEdge MXNet 1G Evolution II Decoder                                                        $791.00 $3,164.00
-               2 Shure Linear Mic Array Bar, 4-Foot (White)                                                                         $2,717.00 $5,434.00
     2 HP HP Elite Mini 800 G9 i713700T 16GB/256GB PC Intel Core i7                                     $2,660.00 $5,320.00
ss              4  Magewell USB Capture HDMI Gen 2 One-Channel Dongle - USB 3.1/3.0/2.0/USB-C                   $385.00 $1,540.00

Confidential Proposal
R25P255 Version 1.0e June 12, 2025
6 of 10 Valid Until: June 26, 2025

Source page 69

IMAGE

A?

REV-T

vaste Infngg WE

Qiy

REV-
Technology Simplified For Better

DESCRIPTION

Audinate Dante AVIO USBC IO Adapter 2x2

REnVisioning Technology, LLC Miscellaneous Installation Items including cable, wire,

PRICE    PRICE EXT

$157.00      $157.00

connectors, etc.                                                                                                                                     $0.00             70.00
AV SYSTEM TOTAL                                                                                        $54,816.28
SHIPPING AND TAXES                                                  $240.00
SUMMARY
EQUIPMENT TOTAL                                                                                $27,941.00
LABOR                                                                                                     $26,875.28
ADMIN FEE                                                                             $503.41
SHIPPING                                                                                                     $240.00
SALES TAX                                                                                                        $0.00
OPTION #1: VIDEO CONFERENCING TOTAL                                      +$55,559.69

Confidential Proposal
R25P255 Version 1.0e June 12, 2025
7 of 10 Valid Until: June 26, 2025

Source page 70

REV-T

Technology Simplified For Better

ACCEPTANCE

FINANCIAL
EQUIPMENT TOTAL                       $32,979.00
PAYMENT SCHEDULE                                                                        SHIPPING TOTAL                         $230.00
Equipment Invoiced at Project Acceptance
Remainder Invoiced at Substantial Completion                                              ENGINEERING                   $2,638.32
INSTALLATION                        $24,600.00
MANAGEMENT                         $2,910.00
PROGRAMMING                         $4,500.00
LABOR TOTAL                     $34,648.32
ADMIN FEE                            $620.79
SUBTOTAL                   $68,478.11
TOTAL SALES TAX                          $0.00
PROJECT TOTAL                 $68,478.11

OPTIONS Not included in the project total. Initial to the left to add the option to your project.
OPTION #1: VIDEO CONFERENCING            +$55,559.69

Confidential Proposal
R25P255 Version 1.0e June 12, 2025
8 of 10 Valid Until: June 26, 2025

Source page 71

REV-T

Technology Simplified For Better

TERMS

| accept this proposal and hereby authorize REnVisioning Technology, LLC to proceed with the installation of the included systems at the facilities of Canton
Public Library constructing at 786 Washington St Canton, MA 02021 as described in this document. | further authorize REnVisioning Technology, LLC to be
granted the facility access that will be required to complete this project and for payment to be made to REnVisioning Technology, LLC, in keeping with the Terms
of Payment listed above. It has been made clear to me that there no understandings regarding this project exist with any relevant party unless and until Canton
Public Library and REnVisioning Technology, LLC agree to such additional or alternate understandings in writing. Project cost and pricing are dependent upon a
continual flow of work without interruption or delays imposed by Canton Public Library or their staff, construction, other building trades or any other party, and
additional costs may be incurred by Canton Public Library from REnVisioning Technology, LLC. If such delays result in additional costs that are not covered by
the pricing in this proposal: | agree that any additions to and/or deletions from the materials and labor to be provided by my acceptance of this proposal and any
resulting change(s) in cost of this project shall only be by way of written change order(s) and shall be valid only after being signed by Canton Public Library and
REnVisioning Technology, LLC. This proposal is valid only if accepted in writing by Canton Public Library.

Warranty: We have included a 30-day labor warranty for the installation of this project. This warranty is not an extension of any manufacture warranties. We
honor all manufacture warranties. The warranty starts at sign off no later than 3 business days from completion of the project. Example: If a device fails in its first
30-days, we will provide remote and/or on-site support. If needed, we will work with the manufacturer for repair or replacement. If the device is no longer under
manufacturer warranty the cost of the repair, excluding REnVisioning Technology's labor, will be billed (if approved) to the owner of the failed device.

Labor Costs: All labor costs in this proposal are based on REnVisioning Technology’s staff, non-union personnel. This proposal does not include weekend hours.
Requirement for Union or prevailing wage rates shall be billed additionally.

Return Policy: Any items returned are subject to restocking fees. Custom items are not returnable.

Wall and Ceiling Finish Work:The customer will assume responsibility for repairing, patching and painting all walls or ceiling finished that may be disturbed as
the result of penetrations and mounting procedures.

Electrical Work: Any line voltage electrical work is the responsibility of the customer and is not included in this proposal.

Exclusion of Software Licenses: Only the software licenses specifically mentioned in this proposal are included. No additional software licenses are provided.
Client Responsibility for MS Teams Room and Zoom Room Licensing:Canton Public Library must purchase and deploy any necessary MS Teams Room or
Zoom Room licenses before REV-T arrives on-site for installation.

Client Responsibility for Network Functionality: Canton Public Library is responsible for ensuring network functionality, not provided by REV-T, prior to the
installation of any hardware.

Recommendation for Software Licensing Testing: We recommend that the Canton Public Library test all software licenses at least 24 hours before REV-T's
scheduled hardware installation, as license recognition by the network may take up to 24 hours,

Owner Furnished Equipment (OFE):REnVisioning Technology, LLC (REV-T) is not responsible for the functionality, compatibility, or condition of any Owner
Furnished Equipment. The client assumes full responsibility for ensuring all OFE is operational and suitable for integration. Any delays, additional labor, or
modifications due to OFE issues may result in extra charges. REV-T is not liable for OFE-related malfunctions or failures.

Tariffs: Please note that hardware pricing is subject to change and may be affected by ongoing or future U.S. tariffs and international trade regulations. As a
result, the cost of AV equipment may fluctuate based on factors outside of our control. REV-T will always strive to provide accurate estimates and competitive
pricing, but we reserve the right to adjust hardware costs accordingly if tariff changes impact supplier rates. We appreciate your understanding and will
communicate any significant changes as early as possible.

REV-T shall not be liable for delays or failure to perform any obligation under this Agreement due to events beyond its reasonable control, including but not
limited to acts of God, natural disasters, pandemics, labor shortages, supply chain disruptions, and changes in laws or regulations (including new or increased
tariffs or import restrictions) that materially impact product availability or pricing.

Confidential Proposal
R25P255 Version 1.0e June 12, 2025
9 of 10 Valid Until: June 26, 2025

Source page 72

REV-T

Technology Simplified For Better

. ACCEPTANCE

CANTON PUBLIC LIBRARY

SIGNED                                                                                             DATE

‘PRINT NAME                                                           TITLE

RENVISIONING TECHNOLOGY, LLC

SIGNED                                                                 DATE

PRINT NAME                                                           TITLE

Confidential Proposal
R25P255 Version 1.0e June 12, 2025
10 of 10 Valid Until: June 26, 2025

Source page 73

TOWN OF CANTON
FORM B — FISCAL 2027
CAPITAL PROJECT / EQUIPMENT REQUEST

DEPARTMENT:                                       SUBMITTED BY:

MIS
Louis Jutras

PROJECT / EQUIPMENT TITLE:                                   TOTAL PROJECT / EQUIPMENT COST:
(Must be at least $5,000):

Any contingency should be explained below

Mobile Device replacement

§ 20,000.00

DESCRIPITION:
What is the request for? Example: 4 police cruisers. What are the funding sources (if more than one)?

Data terminals in police cruisers

PURPOSE AND JUSTIFICATION:

Why the department needs this item. If additional space is needed for justification, please add a second page.

Does this further the Town’s Green Policy? Examples: We reviewed the ‘greener’ options; however, the internal combustion engines
remain a requirement for patrol vehicles that must run for longer periods without the ability to charge. We do have hybrid vehicles in
the fleet where the role is applicable.

Replace 2 remaining computers that are not able to upgrade to windows 11. New docking stations,
installation, and accessories

NEED CLASSIFICATION: (Check all that apply)             Department Priority Rank:
,                                                                      (Please rank this request out of your total requests for
CL] Required for Safety                                                 this year: #1 as top priority)

[__] Required by Law or Mandate                                 Priority# © of # FF

im Improve/Expand Service or Increased Efficiency

Expected Useful Life:
Planning Classification:                                                     5 to 9 Years

Planned project or replacement (on the prior year's 5-
* If not planned, please explain in justification

Impact on Dept. Operating Budget:                         Impact to Dept. Revenue:
No Impact            by § 9.00                                  No Impact            by $_0.00

For motorized equipment: Was an electric or hybrid option considered? Please explain below

OTHER COMMENTS OR INFORMATION: (Attach supporting documentation including quote)

SUBMIT

Source page 74

Date: 9/23/25                                                                                                                                  Ryan Garofano

Customer: Canton MAPolice Department                                                                                                                   401-741-8361
Contact: Luis tras,                                                                   AK                                                                                            sales@northeast-mdt.com
Phone:                                                                            A.
NORTHEAST

gry |NEMDT Part

Number | Category                                           Description                                                                                        Extended

114062 Sector Specific SKU - Intel Ultra 5 125U, W/ Webcam, Microsoft Windows 11 Pro
x64 with 16GB RAM, S12GB PCle SSD, Sunlight Readable (Full HD LCD + Touchscreen +

2            14743082          tre stylus, Us Power Cord, aM Rear Camera, WIFl + BT + GPS /Glonass + 4G LTE (EM7511)+ | $3,849.00 | $3,649.00                     $7,698.00
passthrough, Hard Handle, LAN, Smart Card reader, Thunderboh 4x2, 3 Year Warranty
826
Tolal Price Base Configuration                       $7,698.00
iE MDT Part,                                                                                     i
gry | NE MOT Pat) category                     Description                                            Extended
3     4586765 | charger _|GeTAC:Getac 11-16v, 22-32V OC Vehicle adapter / Chaiger(120W for Docking Station)     sioa99 | $109.99          $32997
Havis
3      6251760 | Charge |Havis Charge Guard: €6-X                                   s10197 | $101.97          $205.1
Guard

Havis Tipte Pass-Through Vehicle Dock with Port Replicator & bracket. DC Power Adaptor

2               asec | Dock                                                                                                                                    $249.00 | $e49.00                          $1,698.00
sotd separately (A140)
Habret and Keyboard Mount with Two Telescope Ports 12" Tabla Pont wih GRIP.
sit Mount |T*/S¥H#et and Single Arm with Universal play Bracket with VESA 75, VESA 100 & 2X4
2     sooconr | nssenvon| Patterns (U0801) 10° Keyboard Post with GRP. Tk/Swiel and Double Armwith Teste | 5509 | 755.09          stpi00
Hae vot and Adjustable Tray for 12° Keyboard. Telescopic Mid Section withthe Next
Generation Under the Seat UNIBASE EVOLUTION (See lst of vehicles)
5     taszarar _ | Antenna- [MULTIMAX 5G Ezconnect antenna with single cable Cel/5G, 1 foot pigtail. Bok mount. | gas as | gras gy          iss
Single Cell |color black.
2            raszarz2 | AMEN Jezconnect cable harness with single Cell 14 feet with SMA male connector.                         $49.63 | $49.63,                          $99.26
2           9047313      ata  Description 83 Key, Backlit, Hard key, Touchpad, USB, Two Cables, US                 $295.00 | $295.00                     $580.00
11067 - Intel Core i5-1235U Processor, 11.6" + Windows Hello Webcam, Microsoft
ruggea | Windows 11 Fro x64 with 1668 RAM + TAA, 25608 PCIe SO (user swappable), Sunight
n     enue |) one:    Readable (Full HD LCO # Touchscreen + Hard Tp stylus, US KBD + US Power cord, — | 4 277.09 | $4297.00          peers
AAREteP” | Membrane Backlit KBD, WIFI + BT + 4G LTE + Dedicated GPS + Passthrough, USB Type-Ax2
‘eV | USB Type-Cx1 + Smart card reader, Dual batteries, Touchpad W/ click button, 3 Year B26
Warranty
rT            5094917      aed  V110 Rugged Laptop Docking Station                                                           sso0.00 | $900.00                       $900.00
2                Instat            Instalt__ instalation of Antenna                                                                                                 $200.00 | $200.00                            $400.00
3                Instat             tnstatt [installation of Computer                                                                                              $650.00 | $650.00                          $1,950.00
Discount 0.00%                                                                                                                                       Total Discounted Price Accessories                      $12,240.96

NOTES:                        Name/Date Rank:
FREE SHIPPING                    Signature:
(QUOTE EXPIRES IN 30 DAYS             Date:

‘TERMS ARE NET 30 PENDING PROPER CREDIT APPROVALS
ALLORDERS SUBJECT TO Northeast MOTTERMS & COHDITIONS,
LEAD TIME [S APPROXIMATELY 4-6 WEEKS.

DEVICES ARE BUILT TO ORDER - NO RETURNS/EXCHANGES

Allprices and descriptions are subject to change without notice, This price lists 9 quotation only and is not an order or offer to sell. No contract for sate will exist unless and until one ofthe following occur: 1.) a purchase order has
bbeen issued by you and accepted by Rugged. One or 2.) an order is place on-line and accepted by Rugged.One or 3.) awrillen proposalis accepted by you. The prices contained in this list may not be relied uponas the price at which
Rugged. One will accept an offer to purchase products unless expressly agreed to by Rugged.One in witing, Product specifications may be changed by the manufacturer without notice. Ili your tesponsiblty toverty product
conformance to specifications of any subsequent contrac. All products are subject to availabilty from the manufacturer Prices quoted may not include applicable taves, Sales tax willbe included on the invoice. Products are non-
returnable unless approved inwrting by Rugged. One Technologies within 20 days of invoice date, Those approved reluins may be subject to a restocking fee, Payment terms are available upon credit approval; unless otherwise
stated inviting. terms shall not exceed 20 days rom date of invoice. Questions about these and other terms and conditions should be addressed by your sales representative.

Source page 75

TOWN OF CANTON
FORM B — FISCAL 2027
CAPITAL PROJECT / EQUIPMENT REQUEST

DEPARTMENT:
MIS

SUBMITTED BY:

Louis Jutras

PROJECT / EQUIPMENT TITLE:

Exterior cameras

TOTAL PROJECT / EQUIPMENT COST:
(Must be at least $5,000):

Any contingency should be explained below

§ 23,000.00

DESCRIPITION:

What is the request for? Example: 4 police cruisers. What are the funding sources (if more than one)?

Replacement and additions to cameras at the police station

PURPOSE AND JUSTIFICATION:

Why the department needs this item. If additional space is needed for justification, please add a second page.
Does this further the Town's Green Policy? Examples: We reviewed the ‘greener’ options; however, the internal combustion engines
remain a requirement for patrol vehicles that must run for longer periods without the ability to charge. We do have hybrid vehicles in

the fleet where the role is applicable.

Implementation of recommendation from the police department audit. Existing external cameras
need to be replaced and additional cameras need to be added to cover the front of the building facing

Washington St

NEED CLASSIFICATION: (Check all that apply)
im Required for Safety
i Required by Law or Mandate
CL Improve/Expand Service or Increased Efficiency
Planning Classification:

Unplanned project or replacement

* If not planned, please explain in justification

Department Priority Rank:

(Please rank this request out of your total requests for
this year: #1 as top priority)

Priority # 5 off ra

Expected Useful Life:
10 to 19 Years

Impact on Dept. Operating Budget:
No Impact            by $ 0.00

Impact to Dept. Revenue:

No Impact             by § 0.00

For motorized equipment: Was an electric or hybrid option considered? Please explain below

OTHER COMMENTS OR INFORMATION: (Attach supporting documentation including quote)

SUBMIT

Source page 76

TOWN OF CANTON
FORM B — FISCAL 2027
CAPITAL PROJECT / EQUIPMENT REQUEST

DEPARTMENT:                                                                         SUBMITTED BY:

MIS
Louis Jutras

PROJECT / EQUIPMENT TITLE:                                     TOTAL PROJECT / EQUIPMENT COST:
(Must be at least $5,000):

Any contingency should be explained below

Software upgrades - office suite

$ 120,300.00

DESCRIPITION:
What is the request for? Example: 4 police cruisers. What are the funding sources (if more than one)?

Purchase and configuration of Office 365 licenses with professional services

PURPOSE AND JUSTIFICATION:

Why the department needs this item. If additional space is needed for justification, please add a second page.

Does this further the Town’s Green Policy? Examples: We reviewed the ‘greener’ options; however, the internal combustion engines
remain a requirement for patrol vehicles that must run for longer periods without the ability to charge. We do have hybrid vehicles in
the fleet where the role is applicable.

Current office version is out of support. We can purchase perpepual licenses of the latest version and
use it until it is unsupported or we can move to a subscription model where we can stay current on
the applications and add additional functionality with hosted e-mail, file sharing, and other services

NEED CLASSIFICATION: (Check all that apply)              Department Priority Rank:
,                                                                   (Please rank this request out of your total requests for
im Required for Safety                                                 this year: #1 as top priority)

[_] Required by Law or Mandate                                  Priority# 4 off

C] Improve/Expand Service or Increased Efficiency
Expected Useful Life:

Planning Classification:                                                    5 to 9 Years
Planned project or replacement (on the prior year's 5-
* If not planned, please explain in justification

Impact on Dept. Operating Budget:                           Impact to Dept. Revenue:
Increase              by § 80,000.00                           No Impact           by $ 9.00

For motorized equipment: Was an electric or hybrid option considered? Please explain below

OTHER COMMENTS OR INFORMATION: (Attach supporting documentation including quote)

If we purchase office perpetual licensing that would cost us $135,000. Exchange upgrade would be
$4,800 but we need to pay yearly subscription pricing for e-mail licenses -

SUBMIT

Source page 77

bl TOWN OF CANTON

CLOUD MIGRATION PLAN

Submitted by:

STONEWALL SOLUTIONS, INC.

October 31, 2025

Source page 78

Table of Contents

Project Description........seseesesneenseeesessuanapeaseseesseccecnseecenscoeseoucucucsessesuseneaseneessecenaasooeas3
Project Background & RAtiondle......sccccserseesssseeseeeseeeasseneneveesseneesneesseeuesueeseeeensnntccees3
Current Environment ASsessMeN........0000000veeseneeeereneoesdtenensaeeeneeeseeneonsaneeseenereeeesseeees3
On Premises to Microsoft 365 Migration ........0.++06seeeaneneessvesaceversrestacssesseeenesseeeeneesored

Identity Access Management & Licensing.                                                                            5
1. Directory Synchronization Review & Configuration                                                                                   5
2, Conditional Access Policies...                                                                                                     Peres)
3. License Restructure & Optimization                                                                                   Pres)
4. Governance                                                                                                                                wl
Exchange Migration........ccscsecccssssneessccccsseecnseeeessnesessaeensessscesenseeeeersaneeesseeeeeeseeeteneeneenee 8
SharePoint and OneDrive Migration ............cscccsesseesseseencereceenerereeanneeceneeesesterenesesesensennanee 9

Cost EStimates ......ccccceeessceeesevesven eveeesdteeseeoneesceneseaneeseasevaseeeeeseneteenesveneesssveneesdeneeneeees 15

Source page 79

Project Description

Deliver a cloud migration plan with a strategy that enables the Town of Canton to havea
smooth, cost-effective ability to migrate its current on-premises Microsoft Office licenses
and content to the Microsoft 365 environment.

Project Background & Rationale

The Town of Canton currently utilizes a portfolio of software applications for finance and
accounting, assessment and billing, licensing, content management and other systems.
Most applications currently are utilized on-premises,

The industry trend both in commercial and public sector organizations is to migrate core
applications and content to the Cloud. The driver for cloud migration includes:

e Increased security of applications, content and data

e Improved access to systems, data and content

e Scalable capacity to meet growth and peak cycles

e Lower on-premises resource requirements and staff labor costs

e Seamless feature enhancements within SaaS solutions

After an analysis of Canton’s current on-premises Microsoft Office license and usage, this
M365 Cloud Migration Plan lays out the steps to move the Office applications and content to
the Microsoft 365 environment.

_ Current Environment Assessment

Identity & Licensing

e¢ Tenant Type: Government (GCC)

e Authentication: Password hash synchronization (Police Department); MFA via Duo

e Conditional Access: Currently three global admins: Louis, David, and Susan

« Directory Sync: On-premises Active Directory sync used only for Police
Department; 82 users currently synced

¢ VPN: Not required for access (currently open)

e Licenses: 3 Microsoft 365 Apps for GCC licenses, 63 Microsoft Entra ID P1 for
government licenses; 3 Office 365 G1 GCC licenses, and 10 SharePoint (Plan 1) for
GCC licenses

Source page 80

Role Options                                            Count

FT = SharePoint, OneDrive, Teams, Exchange, Office and Backup                             30
FO = OneDrive, Office, Exchange, Backup                                                     25
A= Office, Exchange, Backup                                                        |                  130
E = Exchange, Backup                                                                             65

M365 Applications: 3 subsets of apps; 3 Teams environments for Board of Health
Power Platform: Not currently in use

Intune: No plans for use

Endpoint Security: Sophos in place for both firewall and endpoint

Live Events / Webinars: Zoom may be retained for webinars

Teams Phone: No plans to implement

Teams Usage: Limited to the Board of Health; other departments use Teams
"somewhat"

Zoom vs. Teams: TBD based on licensing and cost comparison

Governance Policies: Missing for Teams; creation recommended

FOIA Requests: Currently handled through paper record searches

Data Retention Plan: None currently in place

Document & File Storage

Storage Architecture: Fully virtual via VSANs; each user has an M Drive (up to 8
folders)

File Shares: Multiple public/private departmental shares; 2TB allocated on SAN
File Migration: OneDrive is in use for simplicity; licensing and migration planned,
but home directories remain local

Primary Sharing Tool: OneDrive

SharePoint/OneDrive Governance: No current policies; recommended to establish
naming, permissions, expiration controls

Migration Risk: Broken links expected; remediation required especially for
interlinked files (Excel, PDFs, etc.)

Access Databases: None on file shares

Central SharePoint Site: Proposed for HR, news, and training communication
Data Retention for Offboarded Users: Emails archived; other data reassigned or
archived within a month

Email

Exchange: Version 2019; 252 mailboxes on-prem; no online mailboxes

Source page 81

e Email Security: Barracuda (inbound/outbound) to be retained post-migration; no
current use of Labels for data protection

e Archiving: Barracuda offers temporary storage during outages but is not a full
archiving solution

e Retention Policies: Not currently used for all users; some user mailboxes have
retention policies for Sent and Deleted Items

On Premises to Microsoft 365 Migration
Identity Access Management & Licensing

A robust and secure identity framework is essential to the Town of Canton’s Microsoft 365
migration. Currently, the environment utilizes on-premises Active Directory
synchronization, while Microsoft Entra ID P1 licenses support identity and access
management across the broader workforce. To facilitate a seamless and secure transition,
our strategy will address four core areas:

1. Directory Synchronization Review & Configuration

We will validate the existing Active Directory synchronization process to ensure all
accounts are represented accurately and comprehensively. This includes identifying and
remediating any duplicate, inactive, or orphaned accounts, as well as establishing clear
procedures for ongoing synchronization administration.

2, Conditional Access Policies

Modern conditional access policies will be developed to safeguard global administrator
accounts, enforce location and device-based restrictions, and enable self-service
password reset (SSPR) capabilities for all users. Adopting least-privilege principles will
minimize risk while maintaining operational efficiency.

3. License Restructure & Optimization
An assessment of current license allocations will be conducted, including:
e 3x Microsoft 365 Apps for GCC
© 63 x Microsoft Entra ID P1 (Government)
e 3. Office 365 G1 GCC
e 10 SharePoint (Plan 1) GCC

Source page 82

All major

*     *
6cc3                                      $40                           $40 * 30 * 12
services

[een                                                                                        $14,400

Microsoft 365 Apps +

Pa  oe ae     SharePoint Plan 1213) 4             ue               $21 * 25 * 12
aut en       Exchange Online Plan 1 18)             $4                     $6,300
P                     Entra P1 ©!
|
Microsoft 365 Apps +                                                      i        %
A(130)  ee mare   Exchange Online Plan 1/0!           Ai                eas 12
Backup                 Entra P1 §)                                           !
E (65)        Exchange,       Exchange Online Plan 1 1l3)             $4                   $4*65* 12
Backup /)                Entra P1                                              $3,120
A
                                               sale               $4,065/month            $48,780/year
Note:

[1] All prices are approximate value and do not include tax. Exact prices can be provided by
navigating the licensing purchase portal on the admin M365 portal or procuring a code
from a preferred licensing vendor.

[2] All prices quoted above are for SharePoint and Exchange Plan 1. There is Plan 2 for
SharePoint and Exchange.

[3] SharePoint and Exchange Plan 2 include Data Loss Prevention Policies. Exchange Plan 2
includes additional storage. Those are not included here, however if needed it can be
incorporated as part of the rollout. SharePoint Plan 2 costs $10/User/Month, and Exchange
Plan 2 costs $8/User/Month.

[4] All prices exclude backup. Backup is using third-party vendors, and it is per user.
Backup Storage cost is in addition to the license per user.

[5] Additional Entra P1 licenses are not included here which is $6/User/Month

$48,780 + $16,200 (Entra)+ $15,000 (Backup) = $79,980

Source page 83

Office desktop apps

Office web apps

Outlook (desktop/web)

OneDrive for Business

SharePoint Online

Teams (chat, meetings)

Yammer

Planner & To Do

Exchange Online (Mailbox)

Archive Mailbox

Litigation Hold

Basic eDiscovery

Data Loss Prevention

Sensitivity Labels (manual)

Legal Hold & Auditing
“AAD PL

MFA (multi-factor auth)

Microsoft Purview portal

Intune (MDM/MAM)

Windows 10/11 Enterprise upgrade rights
Mobile device mailbox policies

Defender for 0365 (Plan 1)

Anti-spam/anti-malware filtering

Viva Insights

Power BI (Pro requires add-on)

Delve & Graph insights
Stream (video sharing)

Copilot for Microsoft 365 (Add-on)
Audio Conferencing (Add-on)

4. Governance

We will implement role-based access control and introduce Privileged Identity

xe KKK KK KKK KKK KKK

Not Required
Not Required

X
X
X
X

Not Required

x
X

Available
Add-on

x x x

xX
Not Required
Not Required
Not Required

xX

x

x

xX

Basic

Not Required
Not Required
Not Required
Not Required

X

Not Required ,

Not Required
Not Required
Not Required
Basic
xX
Basic
Not Required
Not Required
Not Required
Available
Add-on

X

x:

X
Not Required
Not Required
Not Required
Not Required
Not Required

X
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required

Xx
Not Required
Not Required
Not-Required
Not Required
Not Required

x
Not Required
Not Required
Not Required
Not Required

Available
Add-on

Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
x
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
Not Required
X
Not Required
Not Required
Not Required
Not Required
Not Required
X
Not Required
Not Required
Not Required
Not Required
Available
Add-on

Management (PIM) to provide just-in-time administrative privileges and enhanced
oversight. Comprehensive governance policies will be established for administrative
accounts, service principals, and delegated roles to ensure continuous compliance and

accountability.