Canton Conservation Commission 
Pequitside Farm — Tavern Room 
79 Pleasant Street 
Canton, Ma. 02021 
July 16, 2008 
MEETING MINUTES 
PUBLIC HEARING 
Attendance: Chairman — Robert Doe, Vice-Chairman Deb Sundin, Clerk - James Fitzpatrick, 
Dave McLelland, Kate Merrigan, Tom Liddy 
Absent: Robert MacDonald 
Conservation Agent: Robert Murphy 
Recording Secretary: Heather Cahill 
Chairman Robert Doe calls hearing to order at 7:03 P.M. 
Minutes: June 18, 2008 
Motion Made by Kate Merrigan to accept as amended the minutes of June 18, 2008. 
Seconded by Deb Sundin Vote: Yes - 6 No —0 
7:10 P.M. 
GENERAL DISCUSSION 
John Marini Rockland Street (AMOOC) DEP 124-970 
Represented by John Rhoads of Norwood Engineering 
Amended Order of Conditions will need to be readvertised, due to significant change in drainage. 
Mr. Rhoads explained to ConCom that after lengthy discussion with Town engineer and Conservation Agent 
Robert Murphy that there is a significant change in drainage of Flood storage compared to original Notice of 
Intent that was filed. Amended Order of Conditions were to include changes to site grading, sidewalk locations 
and materials, emergency fire access road and modified compensatory flood storage. During field changes 
which were minor but didn't meet the compliance standards established in Town of Canton's Wetland Bylaw. 
Changes include: 
1. Location change and material change for walkways associated with the duplex unit at 25 Rockland 
Street. Material change was brick pavers to cement concrete. 
2. Material change for walkway along easterly face of the 16 — unit building from brick pavers to cement 
concrete. 
3. Sidewalk and curbing added at the driveway entrance on the property of 515 Washington St. Realty 
Trust. 
4. Fire lane was modified. Original plan proposed a 14 foot wide fire lane to run from the end of pavement 
at the building's north face along the easterly landscaped area and out to a paved private way on land of 
Pine Realty Trust. Now proposed to provide three access points to the easterly face of the building. First 
access will be an extension from the current access drive adjacent to the electrical transformer. 
5. Two additional gravel surface fire access points that are partially constructed from the private way on 
Pine Realty Trust property. Access points will require fine grading and compacting, these access points 
have been approved by Canton Fire Department. 
6. Compensatory flood storage requirements are proposed to construct an open storage area at on the west 
bank of Massapoag Brook immediately up gradient of twin culverts. Area will provide compensatory 
storage from elevation 96 to 99. 
1 